Hormozgan Steel plant commissioning delayed by 2 months - 11 Mar, 2010
Iranian steelmaker Hormozgan Steel is to start commissioning of its new slab producing plant 2 months later than planned.

Delays in shipment and in installation of equipment have been cited as reasons for the postponement. Construction is already over 92% completed while to date about 70% of the equipment has been installed.

The new Hormozgan Steel plant will have an annual capacity of 1.5 million tonne of slab. It is located close to Bandar Abbas, one of Iran's main ports on the Persian Gulf.

(Sourced from Steel Orbis)



Today's News
Clips
0blt1 Monday Market Monitor - China - WEEK 05 - No fireworks after holiday
Announcements
0blt1 Iranian steel market trend in week 05 2012 - Billet
News And Trends
0blt1 Monday Market Monitor - India - WEEK 05 - Rally in longs fizzles out
0blt1 Monday Market Monitor - Iron Ore - WEEK 05 - Period of inactivity
0blt1 Monday Market Monitor - Metals - WEEK 05 - Recovery on weekend
Export And Import Levels
0blt1 Monday Market Monitor - EU - WEEK 05 - Longs take lead in slide
0blt1 Monday Market Monitor - Scrap - WEEK 05 - Looses steam on slide in billets


Round_corner2
Currency Rates
03 Feb, 2012
USD 1.0000
AUD 0.9350
BRL 1.7197
CAD 0.9992
CNY 6.3063
EUR 0.7606
GBP 0.6320
INR 48.9864
JPY 76.1995
RUB 30.2110
ZAR 7.6560
Ads_spindia
Ads_spmea